Electricity and communication infrastructure, Green Valley (Residential area)
II- III -IV- V Phase

Prato Group started the turnkey project for the construction of electrical infrastructure systems in June of this year, including the electrical system, lighting and telecommunications. In just ten days it has made progress in 100m of trenching, installation of pipelines, filling, compacting and concrete protection. In the coming days, it is expected to make progress of additional 500 meters of development of this infrastructure as part of the start-up phase of these activities.

Go to business models
COR 1 Building /CORPOELEC

Prato Group in its efforts to carry out meaningful projects for the development of the region, it has consolidated the consecutive development of 75% of the construction of the Operation Center CORPOELEC Network; a Venezuelan state company dedicated to the distribution of electricity. Nowadays, Prato Group is conducting the last activities of finishing touches in the executed civil works.